Follow our project

Are you looking for more information about the construction of OXY or just curious about the process? On this page you can find the different phases of development presented in a timeline. Please keep an eye on this page for further updates along the way.

Timeline image
september 2019

Launch of architectural completion

march 2021

Submission of building permit

january 2022

Relocation of Bpost

february 2022

Temporary usage as student accommodation

september 2022

Start of dismantling work

November 2022

Donnerie event

december 2022

Move of VDB

march 2023

Obtain of building permit

may 2023

Start of facade dismantling

january 2024

Start of structural works

april 2024

Start of techniques

april 2024

Start of finishing

Spring 2024

Start of placement of new facade

Spring 2026

Building completely finished

Do you want to find out more about our project?

Reach out to us and discover what exciting opportunities OXY has to offer.